Those accelerated repair projects at the top are sizable: Norfolk Aggie has multiple buildings, and, for those in Worcester wondering, Challenge and Reach is the Harlow Street building, half of which would be covered by the state: $6M project, $3.1M funded by the state.
Both approved
Coming in for Preferred Schematic Design is Leicester, which is a PreK-8 building on the site of the current Leicester Middle. It's a $69.5M project for construction, total cost of $86.9M.
approved
Preferred Schematic Design: Nauset Regional for addition/renovation in Preferred Schematic Design; total estimated cost of $140M
approved
invitation to Project Scope and Budget:
Amesbury: Amesbury Elementary for a new building at $60.5M: approved
Braintree: South Middle for a new building at $86.5M, which notes their East project will open next week: approved
Bridgewater-Raynham Regional: Mitchell Elementary PreK-2 for a new building for $80M
"thanks for all the support since our roof collapse": approved
Gardner: Waterford Street Elementary for a new building for $89.5M
will replace two elementary schools on a site on Pearl Street (so will they change the name?): approved
Holyoke: Chestnut Street Middle and Peck Middle both new, $62.4M and $70.4M respectively:
nice mock-ups on these; Holyoke of course doesn't have a lot of space, and they're making some thoughtful use of space; the mayor notes that two projects at the same time is unusual
approved
Millbury: Shaw Elementary for a new building of $60.9M: approved (after comment sent in by Senator Mike Moore that his children both went there)
West Springfield: Coburn Elementary for a new building for $69M: approved
Dennis-Yarmouth's project once again on hold due to another lawsuit; will cost the towns "as costs are just going up"
Waltham was hoping to be on this agenda, but still facing eminent domain challenges; are in fact before the court right now
There's some interesting charts presented here about projected changes in project costs over time that are going up on the website.