Showing posts with label boilers. Show all posts
Showing posts with label boilers. Show all posts

Monday, June 19, 2023

Hey, we have an F&O meeting tomorrow!

The Worcester School Committee Standing Committee on Finance and Operations has a meeting tomorrow at 5:30 (IN PERSON, though it will stream online), and the agenda includes not only our (last?) monthly transportation update, but a corker of a facilities update! 

Quoting just a few of the updates on projects I know to be of interest: 

  • on water and heat and cooling: Belmont has a new boiler; Burncoat High and Middle have new domestic hot water heaters; Chandler Magnet has a new boiler; City View has a new boiler, Goddard Elementary has a new boiler; Vernon Hill has a new boiler; Forest Grove is getting two new chillers over the summer; and North High is getting a new chiller this summer.

  • on bottle fillers: The SWIG (School Water Improvement Grant) project has started with initial demo of existing fixtures. A 3-month grant extension has been approved through the end of September. Installation of new water bottle filling stations fixtures to take place over the summer, followed by required sampling.

  • on ADA accessibility: Deborah Ryan Associates studies nearly complete for the following schools: Thorndyke, Gerald Creamer Center, Harlow Challenge & Reach, Columbus Park, and Lincoln Street. Draft reports have been provided for comment, with final reports anticipated Summer 2023. Construction has started on the accessibility updates at Worcester Arts Magnet (triggered by the roof replacement).

  • on Burncoat High and NEASC:  Four firms have been engaged to prepare baseline reports and potential courses of action based on the findings of the NEASC report. These studies include building envelope, accessibility, mechanical systems, and traffic analysis improvements. These studies are now complete.

  • on traffic management: Mount Vernon Group Architects have done traffic and pedestrian design studies at both Burncoat Middle and High and at Roosevelt. There is insufficient funding (as we've discussed) in both cases, though Facilities is looking into options to manage some of the issues of concern. 

  • on Burncoat bleachers: project now awarded to a contractor; it is anticipated this will be done for the fall opening of school. The gym floor is also being refinished as part of the same project. 



  • on Elm Park's gym: New wooden flooring is installed, and one coat of varnish has been applied. Roof repairs were undertaken to ensure new flooring system would not be damaged. New doors were installed at South entrance to minimize water infiltration at that location. Vendor is expected to be applying final polyurethane and markings over the next month. The gymnasium walls have also been painted, and new bleacher system installed. Anticipated completion by August 2023, ahead of the start of new school year.


  • on the Honeywell districtwide ESSER funded HVAC updates: $22 million investment, across majority of schools in the district. Scope includes automated controls upgrades, exhaust fan replacements, rooftop units, heating systems. Project will be completed in phases, with on-going work though the Fall of 2024.

  • on the new Doherty: is now weather-tight. It's on schedule for opening Fall of 2024.

  • on school moves: there are moving contracts for both the Alternative school and for La Familia; both moves starting on June 21 and will be done by June 30.

There's LOTS MORE over on the agenda, so go check it out, and maybe plan to at least watch our meeting tomorrow! 

Thursday, August 25, 2022

August Finance and Operations: facilities

 F&O met on August 15 and reported out at the meeting on the 18th, but I'm still getting questions on things connected, in particular, to the Facilities report, so I'm going to write up my notes here from that. The agenda is here and the presentation we received at that meeting I've shared over here.

First up, please note: like many other sectors, the Facilities department is running short-staff (and there are openings!); as of the 15th, there were 28 custodial vacancies. As Mr. Bedard noted: Realize how this works, incidentally: we don't leave schools entirely uncovered, so this necessarily means shifts happen across the system to ensure every building gets coverage. That does mean, though, that some places don't have all they need as a result. 
The summer work to get schools ready for back to school has been going on, and the field prep for athletics is also ongoing.
ON THIS AND EVERYTHING ELSE: supply chains supply chains supply chains...we can only get things as quickly as we can get them. That matters a lot whether we are cleaning or fixing or replacing things, so please be patient.

Regarding the environmental management of the district: water sampling for testing of lead and copper was competed in the spring, and fixtures are being turned on and off and signage is being updated. Watch for further communication updating that. 
Quarterly PCB inspections are scheduled for Doherty and Burncoat; the asbestos three year inspection are ongoing. 

The $150,000 water bottle filling grant (!) was accepted at the August 18 meeting. That state grant provides for bottle filling stations (under very particular parameters) at the following places: 

If your school isn't on here, either it's among the newer schools that may already have them OR it didn't fit the parameters of the grant. We are doing some planning for additional such stations, though, through federal funding.
We have only now received the funding for this: please note that these now have to go through procurement and planning and installation (don't look for them next week; they're not there yet!).

Please join me in being unsettled by the lack of boiler in this space 
(note there is one next to it)

There are boiler replacement projects at Belmont, Chandler Magnet, City View, and Goddard; a boiler replacement is in the planning stages at Vernon Hill. Note that most of our boiler replacements in recent years have been at least partly funded through MSBA (through the accelerated repair program), but we can't always wait to go through the process (boilers are a necessary thing). With fifty buildings (most of which have more than one boiler) that have had underfunded facilities needs for decades now, there's a significant amount of need. 

The BIG project this summer is the Worcester Arts Magnet roof (which is an MSBA Accelerated repair project): 
My photo of the new WAMS roof going in.
The roof will be done this summer; the ADA upgrades (triggered by the cost of the roof) will be done next summer.

There are new hot water heaters going in at Burncoat High and Middle Schools (that's abbreviated DHM for domestic hot water, which is a thing that I learned for this meeting). 
Also at Burncoat High: bleachers in the gym! The bleachers were just going to be pull-out bleachers, but the company has told us that they, given the weight at the size, need to be motorized for safety. Those then are needing some more planning before replacement. 
Also at Burncoat High: the new window blinds are being produced!

GENERAL BURNCOAT STATEMENT: Please note that two things are true at Burncoat:
  1. It continues to be next one being voted by the Worcester School Committee and Worcester City Council for major renovation or repair. Eleven years ago, we opened new North; last year, we opened a new South; new Doherty is under construction. We have had a very strong relationship with the Mass School Building Authority, where we have--unusually!--been able to have two major projects going at the same time. With South now open, fingers crossed on getting Burncoat in.
  2. Burncoat High is undergoing its every-ten-year NEASC reaccreditation. As part of that process, the reaccreditation committee has come back with a report on the facilities, with their concerns. That's in the process of being reviewed and sent out for further study. Even as we plan to replace the building, it's obviously still being used as a school, and so those two things need to be held in balance. 
Claremont locker repairs are being scheduled.
The Elm Park gym floor is being torn up (may be completely up now!) before the layers of waterproofing and other underfloor prep happen before the new one can go in. This is going to take some time
Greendale Head Start has a new parking lot.
The walk-in refrigerator at Norrback is in the engineering stage.
The fire alarms are being replaced at West Tatnuck (it won't be done before school starts, but the old ones weren't taken out yet, so the school has them).
Grafton Street's cafeteria ceiling work will be done before school starts. 

A word on elevators: the Vernon Hill freight elevator was raised at the meeting, but I have been asked about others; we do have several elevators where the issue is beyond waiting for a part (which has been a thing, certainly), and is into questions of replacement (which is very expensive). Thus some of those are much longer term discussions. 

Finally, watch for updates in the future (probably our next F&O meeting on September 8) on the Honeywell and Nault Siemens review of our HVAC systems for upgrades through ESSER funding. Because that is a capital expense, it had to be reviewed and approved by DESE. 

As always, if you have questions, comment or get in touch! 

Wednesday, September 5, 2018

Worcester School Committee meets Thursday

Sorry, late posting on this
The Thursday agenda (back, note, to its regular 7 pm time) is mostly a Finance and Operations-related agenda, even setting aside the F&O report from the meeting today at 5.

Today's F&O meeting has the final account summary for FY18, an excruciatingly literal referral of page 415 of the budget book (on indirect costs), and a single page response to a list of queries from Miss Biancheria regarding facilities.
There is also an extensive update on summer work. There is A LOT (and this includes an update on South High construction!). Of concern: note in particular the list of failed boilers that have had to bump other projects; I'm counting Flagg, Wawecus, and Tatnuck Magnet as either failed or "of concern," which, along with the Claremont controls project, are bumping boiler replacement at Chandler Mag, Rice Square, Lincoln Street, and Burncoat Middle. Also, we're replacing boilers at Doherty and Burncoat High, too? And I imagine we've...like maxed out our accelerated repair projects or something, so these aren't split with MSBA? There is a LOT there; go look at it!

On Thursday's agenda, there are some recognitions. There is NO report of the superintendent. There's a posting of a non-specific executive session.

A series of reports are back, cleaning up from the budget:
There is a response on the reduction of outside vendors (specifically looking at applied behavioral analysis).
There is a (much less extensive) response on summer work PLUS a note on Harlow Street School.
There is a response on snow removal (in sum, it's in more than one acccount because it needs to be).

There is a response to an item on tutors which summarizes all action stemming from the final FY19 budget being larger than the House budget (THIS IS WORTH REVIEWING), and including a nice little summary of where we're at on FBRC. This also notes that the district budget isn't really done until the city sets the tax rate in the fall.

There's a list of which positions are funded how in the Teaching and Learning section of central admin.
There's a past year's positions list in the maintenance department.
And there's a list of where there are security personnel.

There's a somewhat vague update on Doherty High: design firm to be selected in November, then review process with community (hey school committee members: INSIST ON SEVERAL PUBLIC MEETINGS! Make the process more like Nelson Place and less like South). The exact same backup accompanies the following item on Burncoat.

Apparently, the Committee is discussing the "Cultures of Innovations" section of the strategic plan. I hadn't realized this--had anyone?--but apparently they were discussing each section (quickly) during the summer. The plan is to adopt the whole thing Thursday night as well. What connection this has with having referred the plan for review to subcommittees, I don't know. Clearly, someone just wants to get it through without an extensive review process.

For reasons that are unclear, the administration is proposing what it is calling a policy on absence, though it appears to me to be language that pushes a notion of truancy. The administration's worrying focus on bringing back draconian (and unsupported) language, and, one supposes, action, around student absences I imagine stems from the state's change in the accountability system. It strikes me, though, that this is going to do nothing more than run more families (what to guess which ones?) into state oversight, more students into conflict with the school system, and won't actually keep more kids in schools.

There is a suggestion for a Municipal Government Day.
There is a request on for an update on the CPR training.
There is a request for an update on South High (which if someone is paying attention, will be filed, since they got one).

Finally, reading between the lines on administrative requests: TRANSPORTATION:

gb #8-259 - Administration (August 28, 2018)
To authorize the Administration to enter into contracts for the lease of property for a term of up to twenty years for the operation of student transportation for a contract term to begin in June 2020.
gb #8-260 - Administration (August 28, 2018)
To authorize the Administration to enter into contracts for the lease of school buses, special education school buses, and wheelchair buses for a term of up to five years for the operation of student transportation for a contract term to begin in June 2020.

Leasing buses and finding space for them...this is bringing transportation back in house!

No promises on live blog. 

Friday, June 19, 2015

Capital priority projects for FY15

This list is not exhaustive and does not include MSBA projects; this is from admin responses to items involving the budget.

  • Jacob Hiatt roof top units (this is their HVAC system, which was already supposed to be done, that you might remembering my mentioning at our last meeting. We've had a holdup in the crediting of reimbursement)
  • Worcester Tech compressors (two of them)
  • Boiler replacements for the Taylor Building, Foley Stadium, Mill Swan (none of which are MSBA eligible because of not having students in the buildings) and West Tatnuck (where the boiler broke after this winter and must be replaced before fall).
  • Tatnuck Magnet wall replacement (outside)
  • Parent Information Center paint trim (the PIC is made of brick but has wooden gingerbread trim)
  • Jacob Hiatt front plaza and side stairs (stonework)
  • Lake View wall replacement (outside) 

Monday, June 8, 2015

Happy 100, Columbus Park School!

Columbus Park School is celebrating their 100th birthday this year!

We do have schools that still have corridors that look like this:


BUT—facility geek alert—the boilers aren't that old. These were MSBA approved for funning in 2013 and went in last summer. 

Wednesday, March 18, 2015

Five year plan on MSBA accelerated repair submissions (windows, roofs, boilers)

As I mentioned on Monday, part of the updated Facilities report is a five year plan on submissions to MSBA for accelerated repair. Those are the window, roof, boiler repairs that we've done across the district over the past several years. This isn't written in stone--submissions have to be approved by the School Committee and the City Council each year--but it does give us an idea of where we're heading, at least until we get the comprehensive master plan.

2016
Chandler Elementary: windows
Wawecus Road: windows
Belmont Street: windows
Creamer Center: boiler, roof, windows

2017
Midland Street: roof
Vernon Hill: boiler, roof
Thorndyke Road (rear): windows
Lake View: roof
Rice Square: windows, roof

2018
Elm Park: boiler, windows
Sullivan Middle: boiler
Lincoln Street: boiler

2019
Tatnuck Magnet: roof
Caradonio New Citizens: roof
UPCS: roof
McGrath: roof
WAMS: roof

2020
Gates Lane: boiler, roof
Burncoat Middle: boiler
Clark Street: boiler, roof
City View: boiler,
Union Hill: roof


Tuesday, January 20, 2015

Joint Finance and Operations/ Education subcommitte TONIGHT!

with apologies for the late update...I've been out of commission for a few days

There is a joint meeting of the City Council Education committee and the School Committee Finance and Operations subcommittee. We're meeting tonight at 5:30 pm at City Hall.

You can find the agenda here, though the agenda itself doesn't tell you much more than that we're meeting. The real information is in the backups.
There is a facilities update, including the great news on both Nelson Place and South High from last week, and including administration's recommendations for accelerated repair projects, which are:
  • Flagg (windows)
  • McGrath (windows)
  • Grafton Street (windows, boiler)
  • Jacob Hiatt (windows)
The F&O subcommittee votes these, then the full School Committee, then the full Council, before they are submitted to MSBA. The Statement of Interests are due by April 10 this year. 

We also have the transportation information, much of which you know already if you have been following this. What's new is the School Bus Consultants report, which comes with an attached memo from administration regarding their findings. 

While we don't have a written update on budget, I wouldn't be surprised if Mr. Foley asks for one at the meeting. 

Tuesday, October 28, 2014

Joint Committee: Facilities update

backup is here
Allen: $8 million matched by $32 million from state on facilities updates (windows, roofs, and boilers)
can tell updates as you drive by the building
in schmematic design phase for Nelson Place
"project is moving right on schedule"
South High has had a senior site visit; MSBA has toured the school
reviewing 108 projects for the core program, we're told
facilities master plan: joint effort between schools and city
internally have done two schools to get a baseline to see what information needs to be collected
pilot contracted out Doherty
what's the best way to proceed?
hope to have by end of FY14
Toomey: creative funding; some question around private funding; is there the same type of investment in technology?
Zidelis: a sale/leaseback: "we continually look for non-conventional ways to fund projects"
Economou: WPI and Doherty: could WPI build a new technology wing for Doherty?
Allen: has been conversation with local colleges from school side. not sure to what extent in facilities, but would pursue if available
Foley: would be difficult for a college to build something for a public school; can bring students onto campus
Toomey: state sells bonds, where are we on that?
Zidelis: that's what we do
Toomey: do we have a breakout of that process?
Zidelis: yes, have that information as of end of FY14; also in auditor's report
Novick: Boston building a new Mattapan High without going through MSBA; bonding out entirely (though possibly not most needed facility at this time)

Thursday, July 3, 2014

Finance and Operations (mostly operations) update

Today's (early) Friday letter includes a Finance and Operations memo, which you can find here.
  • First up, the annual school choice report, in both directions: 480.5 students choicing out, 85.2 choicing in. The district receiving the largest number of WPS pupils is West Boylston (that's a change, incidently; it's been Wachusett for a number of years) at 130, followed by Wachusett (109), Berlin-Boylston (65.3), Leicester (29.4), and Auburn (20.7). We're receiving the largest number of students from Shrewsbury (14.4), Leicester and Wachusett (11 each).
  • The summer feeding schedule is also forwarded, but you can also find it here. Any child under 18 can visit and get lunch Monday through Saturday, save July 4 and 5. Locations include all library locations (including the schools), Union Hill School, and both state pools. Please pass this along to anyone in the city who could use the information. Summer can be a hungry time for kids.
  • We also have the solar panel update. Roof coatings ahead of the panels going in looks as though it's mostly complete; most panels are going in now, 'though South's will be going up in September, and Norrback's in November.
  • As for MSBA (you got some of this already, so I'll give you what's new), it looks like Worcester Arts Magnet and Columbus Park will have their windows for school, or shortly thereafter; no date on Chandler Magnet, but that's finishing a second year, so let me check; Tatnuck Magnet is going to be a second shift in the fall job, as May Street and Lake View were last year, due to window manufacturing schedules; and the boiler replacement at Worcester East Middle is a complicated project, so we may be looking at a temporary one come fall (boy, I hope not!).
Let me know if you have questions!


Tuesday, June 24, 2014

Summer building work

There are often projects going on in our schools over the summer; this summer, we have several BIG projects happening:

  • Worcester East Middle School is getting new boilers.
  • Chandler Magnet School is getting the rest of their new windows. They're also getting the roof work and solar panels done, thus the flags around the roof.
  • Worcester Arts Magnet School is getting new windows, as well as some work done to the vestibule and the bathrooms.
  • Columbus Park is getting its new boiler, as well as having the new windows installed.
  • Tatnuck Magnet is getting new windows.
Good stuff! (And thanks, MSBA!)

Monday, May 19, 2014

Signs of Worcester's industrial past

More unseen corners of the Worcester Public Schools...today: the Worcester East Middle School's boiler room.
When Worcester East Middle School was opened in 1923, Calvin Coolidge was in the White House, a first class postage stamp was two cents, and the newly opened Grafton Street Junior High School was heated with three massive boilers that burned coal.
Much of that has changed, but the boilers are still there, having been converted over their history first to oil, then to natural gas.


It is difficult to get the sheer size of these boilers. These photos were taken from a basement-level catwalk over them; the boilers themselves are a story and a half or so down further. Each is the size of a steam locomotive. They are massive.


The boilers were manufactured here in Worcester at Stewart Works (as you might be able to read on the doors, which say STEWART BOILER WORKS  WORCESTER, MASS  1923). The Worcester Historical Museum has a photo posted of workers shoveling coal into just such boilers. 


 Of Stewart Works, Ellery Bicknell Crane in Historic Homes and Institutions and Genealogical and Personal Memoirs of Worcester County, published in 1907 has this to say: 
THE STEWART BOILER WORKS of Worcester, well known throughout the New England states, and which stands high among the leading industries of the city of Worcester, sustaining a reputation for thorough workmanship and honorable dealing, has since September, 1888, been under the ownership of James C, John C. and Charles M. Stewart, sons of Charles Stewart, a native of Glasgow, Scotland, who learned his trade in England. Upon his arrival in Worcester, Massachusetts, Charles Stewart began manufacturing boilers for Bellows & Whitcomb, who were at that time engaged in building portable steam engines...In September, 1889, the works were moved to new shops at the present location, Albany street. The plant is extensive, covering a space of nearly two acres of land located a half mile east of the Union station, and on the line of the Boston & Albany Railroad, and easily accessible from all parts of the city of Worcester by means of the electric cars. The main building is sixty by three hundred and seventy feet, and there are a number of smaller buildings for various purposes, all admirably equipped with machinery, There is a spur track running alongside the works, and with a powerful electric hoisting crane gives excellent facilities for receiving and shipping goods. The firm manufactures locomotive, marine and tubular boilers, tanks for oil, water and general purposes, smoke stacks, penstocks, and heavy plate iron work of all kinds. They also attend to repairs of boilers in mills, etc. They employ on an average seventy-five men, many of whom have served at the works for a long period of time.



As the boilers burned coal (and large amounts of it), there were doors that have onto the street for coal delivery through a chute:

Up until recent years, there was still a "fireman" designation in the Worcester Public Schools custodians' contract, from the days when it was an additional custodial duty to keep these stoked with coal to heat the building.


These are among the projects for this summer, as the Mass School Building Authority has committed to funding 80% reimbursement on replacement. 

While the School Committee member part of me is relieved that we aren't trying to nurse these through another winter, with school plant welding things back together in a frigid building, and the utility costs these entail...the Worcester history buff is a little sad to see them go. 

Wednesday, January 29, 2014

Here we go: boiler for Worcester East Middle

Worcester East Middle School boiler APPROVED!
also note that all of the list below were also approved for their respective recommended actions

Worcester East Middle before MSBA

Posting today from the Mass School Building Authority board meeting, where Worcester East Middle School's boiler replacement is on the agenda for authorization of the project funding agreement (aka: they're going to pay for, in our case, the 80% of the project).

Project total cost is $2,865,498 of which MSBA is recommending to their board payment of $2,064,010.

Also on the agenda for today are invitations to eligibility for Billerica, Carver, Hanover, Provincetown, Quincy, Somerville, and Stoughton.
Dedham is being invited to Feasibility for their Early Childhood Education Center.
And $37,611,713 in accelerated repair projects (including Worcester East Middle) are in for authorization of their project funding agreements; those are in 21 cities, towns, and districts.
Haverhill is putting forward a preferred schematic design for a $50 million new middle school.
Gloucester (West Parish School) and North Middlesex (for their high school) are being invited to project scope and budget. Gloucester's is a $39 million project and North Middlesex's an $89 million project.

I'll post as I have news!

Wednesday, January 8, 2014

Nelson Place boiler

You may have seen the reports regarding the evacuation of Nelson Place today.
Nelson Place School

The Worcester Fire Department and the Facilities Department responded to Nelson Place School for a report of the smell of gas.  Students were initially evacuated and then relocated to the gym, cafeteria, and library within the school.   It appears that a boiler has a faulty exhaust and was emitting fumes back into the school.  The boilers (and subsequently the heat) were shutdown to parts of the building.  Students were returned to most classrooms shortly before noon while others were relocated for the remainder of the day elsewhere in the building because of cold temperatures in the classroom.  It was determined that afternoon preschool could operate safely and warmly within their classrooms and we did not interrupt their normal schedule.  A number of students were dismissed by their parents during the day.  The parents were informed of the status through Connect-Ed message that was sent by the school.

Work to make the necessary repairs will occur this afternoon and evening.

Wednesday, June 5, 2013

This makes nine accelerated repairs for Worcester

And we're in!!
Expect to see those projects as early as next summer!

As a reminder: these projects are:

  • Columbus Park: windows and boiler
  • Tatnuck Magnet: windows
  • Worcester Arts Magnet: windows
  • Worcester East Middle: roof, windows, boiler

Best estimate we have right now is we're looking at projects totalling about $15 million.

Tuesday, June 4, 2013

Worcester school buildings before the state tomorrow!

We've recently gotten word that ALL FOUR of our proposed Accelerated repair projects are before the Mass School Building Authority board tomorrow at 10 am!
As a reminder, those projects are:

  • Columbus Park: windows and boiler
  • Tatnuck Magnet: windows
  • Worcester Arts Magnet: windows
  • Worcester East Middle: windows, roof, boiler
This is great news! Remember, this means we're up for 80% reimbursement on these fixes! 
I will be there and will liveblog the meeting. 

Wednesday, May 1, 2013

Capital spending: repairs

Allen: $7.7 million work at 10 schools, all complete
ESCo: boiler/chiller replacement, boiler replacements are all completed this past year
SoI's last year on Nelson Place, plus accelerated repairs
5 schools in accelerated repair: work will start this summer

  • Chandler Magnet will get windows this summer and next summer
  • May Street will get new windows
  • Lake View will get new windows
  • Jacob Hiatt will get new boiler
  • Caradonio will get new boiler and new windows

O'Brien: how much?
Allen: 80% state funding, bids received, contracts being awarded
$9 million in total, we're funding about $1.8 million
Allen reserving some for environmental work, plus Heard Street roof, masonry at Jacob Hiatt and Vernon Hill
Biancheria: additional sixth grades, in Worcester East Middle, which we promised a science lab
Allen: Worcester East Middle science labs should be bid this week, construction to begin by summer vacation to be done by next school year
completed by fall of 2013
Allen comments that getting bids that has been difficult, getting a successful bid will allow work to be completed for school year of 2013-14
"project budget is a little less than $350,000"
complete school painting jobs: not just classroom by classroom

Thursday, January 3, 2013

Caradonio New Citizens back up and running

Update this morning from school facilities: the heat has been restored to the entire building as of last night, and the students and faculty returned there today.
Thanks to Sullivan Middle for your flexibility yesterday!

UPDATED: And the buses all started on time this morning!

Tuesday, July 17, 2012

Round-up of summer work

I know that several of you have wondered just what is going on at your neighborhood school as you're out and about this summer; as I've gotten several questions, I thought a post was in order.

  • If you've been by West Tatnuck and Worcester Arts Magnet, you may have noticed dumpsters. They are getting entirely new lighting, under an energy conservation deal National Grid has offered. We're only paying a fraction of the cost, and the schools will have new lights
  • New boilers are going in this summer at Union Hill, Worcester Arts Magnet, Quinsigamond, Claremont/Woodland, Roosevelt, and Norrback. Among other things, this rids us of the last of the "born to fail" round of boilers/chillers at those 1990-era buildings.
  • Solar panels are going on at Sullivan and at Worcester Tech; Tech is also getting a small wind turbine.
  • Attic insulation is going in at Quinsigamond, Union Hill (both buildings), Goddard, Harlow Street, Heard Street, Midland Street, and UPCS.
  • Goddard's upstairs bathrooms are being renovated.
  • Tatnuck Magnet is getting some replacement flooring and having the bathrooms renovated.
  • Window sealing, spot light fixture replacement, fresh air intake cleaning and balancing, and surface cleaning is happening this summer at Belmont Street, Burncoat Middle, Burncoat High, Chandler Elementary, Chandler Magnet, Clark Street, Columbus Park, Doherty, Elm Park, Flagg Street, Forest Grove, Greendale, Harlow Street, May Street, McGrath, Mill Swan, Nelson Place, New Citizens, Rice Square, South, Thorndyke, Tatnuck Magnet, Union Hill (new building), Wawecus, West Tatnuck, Worcester Arts Magnet, Worcester East Middle. Exceptions: West Tatnuck and Worcester Arts (as listed above) are getting entirely new lights; May Street, Chandler Magnet, and New Citizens are getting new windows next summer, and so are not having their windows sealed. 
  • There's a huge amount of smaller work (you can find it listed here under the ESCo projects) in the way of water conservation, sensors and timers, building infiltration work (getting rid of the drafts, you might say), and so forth.