So last night, the Worcester School Committee unanimously confirmed Nelson Place as our first priority school. The administration will be confirming that with the Mass School Building Authority in the next few days.
Then we wait.
We could hear back as early as January from the state.
Should the Mass School Building Authority Board vote Nelson Place into the pipeline, we would be notified, and then the city would have 270 days to meet their eligibility requirements. Those include setting up a building committee, gathering enrollment figures, and having the superintendent, city manager, and the chair of the school committee sign a certificate of compliance.
We also would need the City Council to vote the funds for a feasibility study. The feasibility study is eligible for the state reimbursement (probably 80% for Worcester), but it is reimbursement, so the city has to front the money.
The city has a year to complete the feasibility study.
I will post more as I hear more.
No comments:
Post a Comment
Note that comments on this blog are moderated.